Stanley Park Opened in July as a Path and a Pier. The Rest Is Slated for 2027

White Lake Township's own Stanley Park webpage still says the park is "CLOSED as construction for the Phase 1 improvements is underway" and asks visitors to "check back in the fall." Fall is here, and the park opened months ago. The township's 2027–2032 Capital Improvement Plan says the 59-acre park on the west side of Elizabeth Lake Road, south of the White Lake Township Library, "opened to vehicular traffic on July 1, 2026."

The park you can drive into at 10785 Elizabeth Lake Road is the first of three planned phases. Right now it's a road, a path, a pier, some benches and a shoreline. Restrooms, a playground, picnic shelters and a sport court are all in the next phase, and that construction isn't expected to start until summer 2027. If you go before then, you're visiting the quietest version of this park there will ever be.

A Campground Becomes a Township Park

Long before the paving, the land on Brendel Lake was the Brendel Lake Campground, owned by the Pollack family. The township bought it in December 2019 and named it Stanley Park in honor of the late Stanley Pollack. A Michigan DNR grant paid for 74% of the $1.3 million purchase, and the property will remain a park in perpetuity, according to a Lakewood Village neighborhood association update from December 2025.

The planning firm was Beckett & Raeder, which also designed Bloomer Park on McKeachie Road north of M-59 and Hill Road. McCarthy & Smith managed construction. Phase 1 was finished on October 15, 2025. It took a $500,000 grant to build, and the association reported in February 2026 that $450,000 had already been approved for reimbursement, with the last few items scheduled for April and May to meet a June grant deadline.

Here's what that first phase built, per the same update:

  • A paved entrance road from Elizabeth Lake Road
  • A paved walking path down to Brendel Lake
  • An observation and fishing pier on the lake, installed as the old boat ramp was removed
  • Grading, tree work and hydroseeded ground cover throughout

An exercise station was back-ordered last winter and was scheduled to go in after April 15.

What the Parks Committee Saw on Its Walk-Through

The best snapshot of the park as it stands comes from a July 8, 2026 walk-through by the township's Parks and Recreation Committee. A staff memo dated August 6 says members were "generally pleased with the completed improvements." It also lists what they flagged for follow-up.

That list gives a good picture of the place. The park has wheelchair-accessible bench areas, and staff are buying new covered metal trash cans that will be placed so they don't block that seating. The committee wants a plan for phragmites, poison ivy and other unwanted plants along the inside edge of the pathway. The former campground beach is grass and natural shoreline, and the committee generally supported leaving it that way. An accessible kayak launch came up only as a possible "longer-term improvement."

Summer had a problem too. Township Board members asked staff to buy a second Horse Pal fly trap to cut down on deer flies and other biting flies. The memo reports that the first one collected "approximately three to four inches of flies" with no chemicals. The flies were a July issue. In November you'll mostly have the path and the pier to yourself.

Built Now, Planned for Phase 2

Phase 2 is where most of the familiar park features show up. In a draft proposal dated June 25, 2026, Beckett & Raeder and architectural partner Straub Pettitt Mann Architecture laid out the next round of work.

On the ground now In the Phase 2 scope
Paved entrance road Parking lot in the upper park near Elizabeth Lake Road
Paved path down to Brendel Lake Restroom and storage building with a built-in picnic shelter
Observation and fishing pier Picnic shelter next to the fishing pier
Accessible bench areas Picnic pods near the lower parking area
Grass and natural shoreline Playground near the lower parking area
Multi-sport court in the upper park
Park entrance sign
Site prep for a future amphitheater

That's a lot of new infrastructure. The proposal calls for new storm, sanitary and water utilities, plus electric, gas and IT service. Beckett & Raeder's fee is $150,000 for basic services plus $17,500 for outside services, a total of $167,500, and the proposal expects construction in summer 2027. The Township Board approved the design and engineering contract at its September 15, 2026 meeting. The capital plan lists the full Phase 2 cost at $2.25 million: $1.25 million from the township and $1 million from other sources.

The playground has gotten bigger along the way. In June, the committee picked a design that fit within a $75,000 contribution from Kroger and was aimed mostly at ages 5 through 12. Then board members suggested the township match Kroger's money. Staff came back with three concepts on a budget of about $150,000, each with a larger area for ages 5 to 12 and a separate, smaller area for ages 2 to 5. The committee's October 14 meeting was canceled, so the final design is still open.

The Construction Next Door Runs Longer

Stanley Park shares the Elizabeth Lake Road frontage with the township's new 29-acre Civic Center site. According to Redstone Architects, that site will hold a new Township Hall and Senior Center, plus a 46,000-square-foot public safety building for fire and police with a community room for training.

Stanley Park's first phase wrapped up in October 2025, but the Civic Center is running behind. A September 4 construction-management memo from McCarthy & Smith says the Civic Center was originally due in May 2026 and is now forecast for January 2027, about eight months later. The architect's project page and the capital plan both still say fall 2026, so treat any date as a forecast. On the same September 15 night it approved the park design contract, the board also approved a transfer of funds within the Civic Center budget for that longer staffing period. The memo puts the added staffing cost at $250,000, split evenly between the Township Hall and the public safety building.

For a visitor, the stretch of Elizabeth Lake Road south of the library will probably stay an active job site this winter, even as the lake end of the park stays quiet.

Planning a Fall Visit

The township's rules for its parks say township parks are open dawn to dusk all year, weather permitting, and dogs and other pets must be leashed and under control. A few practical points for November:

  1. Go earlier in the day. Dusk comes early this time of year, and dusk is closing time.
  2. Bring what you'll need. The restroom building is part of Phase 2, so plan as you would for a trailhead.
  3. Head for the pier. It's the only spot in the park built for getting out over Brendel Lake.
  4. Keep the dog on the paved path. The committee's notes mention poison ivy along the inside edge of the pathway.
  5. Pair it with the library. The capital plan places the park just south of the White Lake Township Library, which The Oakland Press lists at 11005 Elizabeth Lake Road.

The library has several November programs that fit an afternoon walk. An adult Write-a-thon runs Saturday, November 7, from 10:30 a.m. to 4:30 p.m. in The Gathering Place A & B. A Silent Book Club meets November 14 from 2:30 to 4:30 p.m. On the evening of November 11, from 6:30 to 7:30 p.m., there's a children's Native American Heritage Month storytime featuring "Keepunumuk: Weeâchumun's Thanksgiving Story." All three require registration through the library's event calendar.

The Lakewood Village update said the township was planning a ribbon-cutting at some point in 2026. No date has been announced, and in the meantime the park follows the township's standard dawn-to-dusk hours.

Sheryl keeps an eye on White Lake Township's parks and civic projects, including Stanley Park, the new Civic Center and the plans for the Elizabeth Lake Road area. If you'd like to talk about how projects like these are changing your part of the township, Sheryl Kersten is glad to share what she knows. Let's Connect.